Syncrude Canada 72KV – HV Distribution Project K005 (MLMR)
Provide power requirements capable of supplying 72kV infrastructure systems to new Ore Preparation Plants throughout MLMR. Scope of work included:
- 72kV transmission lines
- 230 structures
- 21kms of lines
Existing 260/72kV substation DO5 modifications
- Upgrade two 100/133/166 MVA transformers
- Up rating six 72kV disconnects from 1200A to 2000A
Addition of a new EO2 Substation
- All civil workers
- Steel structures
- 80/107/133/166 MVA transformers
- P&C building
- Equipment
- Commissioning assistance
- Seven new substation skids 72/4.16V
- Five new tie breaker skids and vac-putors 72kV
- Five 72kV line crossings
- Three 25kv
Project Details
-
Client: FLUOR