ConocoPhillips Surmont II

83,00 BPD SAGD Facility

Completing the electrical, instrumentation and high voltage portion of this world class facility was no small feat.  Understanding critical path, Chemco collaborated with owner, engineering and other contractors during the construction of the facility. With over 1,000 highly skilled tradespeople working multiple shifts, this project was brought online meeting safety, budget and timeline targets.

Civil/Earthworks contract- Installation of underground cable for site wide power distribution and 22 km of underground fiber line from the plant to the well pads.  Work included approximately 2 km of site drainage excavation and backfill utilizing hydraulic excavators, dozers and articulating rock trucks.  Supplied, placed and compacted sand bedding for all installations.  Work was executed during winter months to meet project schedule.

Project Details

  • Client: ConocoPhillips

  • Manhours: 4,000,000